Government supportCompiled by PAPATONYViews 0From our consultations

Subsidy project: personnel budget, change approval, settlement and recovery?

We are a 7-person company selected for a government support project and about to sign the agreement. I am confused about how to budget the CEO's pay and internal staff pay. If we have to change budget items after signing, what procedure applies? What should we watch at settlement, and how are misused funds returned? Can we reuse an earlier application as it is?

A question PAPATONY received in consultations and day-to-day practice, rewritten without any name or detail that could identify the person or company.

Anyone can post a question here

Have a similar question? Ask it yourself, anonymously and without signing in. PAPATONY will answer.

PAPATONY answer

PAPATONYCompany setup · HR · tax practice

The Subsidy Management Act sets the framework for budget changes and settlement, but item-level rules such as whether the CEO's pay counts come from the call for proposals, the grant conditions and the agreement. So do not reuse an old application; read the cost category definitions for this project first. To change how expenses are allocated, get approval before you spend.

Which law applies

  • National subsidies granted by a central ministry fall under the Subsidy Management Act. Subsidies granted by local governments have their own Act, and projects run by public bodies often follow the body's rules and the agreement. Check the call for proposals for the legal basis.
  • Grant conditions may be attached as needed to achieve the purpose set by laws and the budget (Article 18(1)). Caps on cash personnel costs, or whether the CEO's pay counts only as an in-kind contribution, are usually found in these conditions and the agreement (practice).
  • Typical checks when budgeting personnel: social insurance enrollment to separate internal and external staff, separate caps for the CEO and registered officers, unit cost fixed from the last year's payroll register and withholding receipts, and total participation across projects not exceeding 100% (practice). They differ by program, so the cost standard table in the call comes first.

Budget changes need approval before spending

  • To change the content of the project or how expenses are allocated because circumstances changed, you need the approval of the head of the central ministry, except for minor matters that the head defines (Article 23).
  • Handing the project to another operator, or suspending or abolishing it, also needs approval (Article 24).
  • Attach the reason, a before-and-after table and evidence to the change request and keep the approval letter. Costs paid before approval risk being disallowed, so match payment dates against the approval date (practice).
  • Subsidies may not be used for any purpose other than the one in the grant decision (Article 22(1)).

Settlement

  • When the project is completed, abolition is approved, or the fiscal year ends, submit the performance report with a settlement report by funding source (Article 27(1) and (2)). Above a set subsidy amount an auditor must verify it (latter part of Article 27(2)). The deadline is 2 months from the date the reporting reason arises (Article 12(1) of the Enforcement Decree).
  • Late filing can cut the next payment: up to 10% for 3 months or more, up to 20% for 6 months or more, up to 50% for 12 months or more (Article 12(3) of the Decree).
  • The ministry reviews the results, conducts an on-site check if needed, and then fixes and notifies the amount (Article 28). It can order corrective action if the results do not comply (Article 29).
  • You must report progress, accept on-site inspection and keep related records for the required period (Article 25).

Recovery and sanctions

  • Use for another purpose, violation of laws or the grant decision, and false applications can lead to cancellation of the grant (Article 30(1)); the cancelled portion plus interest must be returned by the deadline (Article 31(1)). If you received more than the fixed amount, the excess is returned too (Article 31(2)).
  • A recipient who obtained funds by improper means or used them for another purpose is ordered to return them (Article 33(1)) and, once the conditions such as the number of violations are met, may be excluded or restricted for up to 5 years (Article 31-2(1) and (2)).
  • Duplicate or excessive applications can be reflected in later budgets, so before applying again, list your agreement projects, recent subsidy totals and participation rates in a table.

General information as of the answer date, not advice for your specific case. Check with a licensed labor attorney, tax accountant or lawyer before acting.

Guides on this topic