Construction revenue in Korea: progress method for contracts and presales
For builders and developers in Korea: how tax law spreads contract and pre-sale revenue by a progress ratio, how the ratio is set, and when handover timing applies.
At a glance
- Default rule
- Revenue by progress ratio from start of work to handover
- Progress ratio
- Cumulative construction cost ÷ total estimated cost
- Handover option
- SME contracts under 1 year, or handover-based books
- Pre-sales
- Only signed sale contracts enter the contract amount
- Interim payments
- Up to 60% (70%), split around the 50% cost point
Construction companies that take contract work and developers that pre-sell apartments earn their revenue over several years. Korean corporate tax law spreads that revenue over the build period using a progress ratio, and allows recognition at handover only in a few cases. This guide sets out the tax rule as of November 2026, how the ratio is worked out in practice, and how the accounting standard for small companies lines up with it.
The tax rule: revenue follows the progress ratio
Under the Corporate Tax Act (법인세법), income and expenses belong to the business year in which they become fixed (Article 40). The Enforcement Decree applies this to construction, manufacturing and other services, and it expressly includes contract work (도급공사) and pre-sales (예약매출, selling units before they are built) (Decree Article 69(1)).
From the business year in which the work starts until the year of handover, each year's revenue and costs are calculated by the progress ratio (작업진행률). The Enforcement Rule gives the formula (Rule Article 34(3)):
| Item | How it is calculated |
|---|---|
| Revenue for the year | Contract amount × progress ratio at year end, minus revenue already included in earlier years |
| Costs for the year | Total costs incurred in the year |
If a contract is cancelled and the amount finally settled differs from what was recognised by progress, the difference goes into the year of cancellation (Decree Article 69(3)).
How the progress ratio is worked out
For construction, the progress ratio is the cumulative construction cost incurred up to the end of the business year divided by the total estimated construction cost (총공사예정비) (Rule Article 34(1)). The total estimated cost is the cost estimated at contract time under accounting standards, updated for changes up to the end of the year (Rule Article 34(2)).
There is one alternative. If revenue moves in proportion to work hours, work days, or the area or quantity of completed work, and the completed share can be measured objectively, the company may use that physical ratio instead.
Practical points from site accounting:
- Korean site teams work from the execution budget (실행), the estimate converted into the actual construction plan. Comparing costs incurred with the execution budget is, in effect, the progress ratio. When the execution budget exceeds the contract price (an execution rate above 100), the project is loss-making.
- A feasibility study (사업성 검토서) is a projection, not a total estimated cost. Using it as the denominator tends to understate costs and overstate progress. Build the estimate from contracts, quotes, design and supervision agreements.
- Advance payments for construction (선급공사원가) enter the ratio only when the work they pay for has been carried out.
Developers who hire a contractor
Many developers do not build themselves. National Tax Service (국세청) rulings explain how they compute the ratio:
- The cumulative cost is the developer's own direct construction costs plus the total contract price owed to the contractor multiplied by the contractor's progress ratio (ruling 법인세과-760, July 2, 2009).
- Construction costs include insurance, design fees and technical support fees that the developer pays directly, as well as the contract price (ruling 법인세과-2354, September 5, 2008).
Land, advertising, the model house, sales agency fees and interest are not construction costs, so practitioners keep them out of both parts of the ratio. When the contractor's figures arrive late, a common practice is to estimate progress from the progress certified by the construction supervisor (감리확인공정률) and adjust the following month when the contractor's tax invoices arrive.
Pre-sold housing: which units count
The contract amount in the formula is the price in sale contracts actually signed, so units that are still unsold produce no revenue until a contract exists. In practice this is expressed as a sales ratio (분양률). Most practitioners measure the sales ratio by sale price rather than floor area, because prices differ by floor and use.
For apartments, the handover date that ends the progress period is the earliest of the ownership transfer registration date, the date the balance is settled and the move-in date (ruling 법인세과-1151, October 16, 2009).
Construction services and housing supply also have their own VAT timing rules and a housing exemption, which a separate guide on this site covers.
When revenue can wait until handover
The decree allows the handover year instead of the progress ratio in three cases:
- A small or medium enterprise (중소기업) performs a contract that lasts less than one year (Decree Article 69(1)1).
- The company books the revenue in the handover year under the accounting standards it applies (Decree Article 69(1)2).
- The company has no books, or its books are too incomplete to confirm the cumulative cost or work hours at year end (Decree Article 69(2), Rule Article 34(4)). This is not a choice; it is the result of poor records.
The accounting side for small companies
Stock companies that are not subject to external audit and are not public institutions use the accounting standard notified by the Ministry of Justice, the SME Accounting Standard (중소기업회계기준) (Enforcement Decree of the Commercial Act, Article 15; Standard Article 2). Its Article 24(2) says that service and construction contracts are recognised over the period by progress when the progress, the costs incurred and the costs to complete can be measured reliably. Contracts completed within one year may be recognised when the work is finished. Companies under external audit follow the standards set under the External Audit Act instead. Where their standard leads to revenue at handover, Decree Article 69(1)2 lets the tax return follow it.
Instalment rules for pre-sold housing
The Rules on Housing Supply (주택공급에 관한 규칙), Article 60, limit what a developer can collect before completion:
| Payment | Limit and timing |
|---|---|
| Application deposit (청약금) | Up to 10% of the price, at the call for buyers |
| Contract deposit (계약금) | Up to 20% including the application deposit, at signing |
| Interim payments (중도금) | Up to 60% of the price (70% if the contract deposit is 10% or less) |
| Balance (잔금) | After the use inspection (사용검사) |
Interim payments are tied to the point at which 50% of the total construction cost, excluding land, has been spent, with each building at least 30% complete. They must be split into at least two payments before and two after that point (one each if interim payments are 30% of the price or less). No more than 50% of the interim payments may be collected before that point, and the first may not fall due until one month after signing. A private developer must obtain a construction progress certificate (건축공정확인서) from the supervisor and submit it to the city, county or district office before calling the first interim payment after that point.
Checklist
- Set the total estimated cost from contracts, quotes and design and supervision agreements, and update it every year end.
- Reconcile the cost-based ratio with the supervisor's certified progress and keep the reasons for any gap.
- Keep a year-end list of signed sale contracts and their prices.
- For contracts under one year, check whether the company is an SME before using the handover year.
- Record cancellations and the settled amounts in the year they happen.
Korean terms you will see
| Term | Reading | Meaning |
|---|---|---|
| 작업진행률 | jageop-jinhaengnyul | Progress ratio: cumulative construction cost divided by total estimated cost, used to spread revenue. |
| 예약매출 | yeyak-maechul | Pre-sales: selling apartments or other units before they are built. |
| 도급공사 | dogeup-gongsa | Contract work done for a client at an agreed price. |
| 총공사예정비 | chong-gongsa-yejeongbi | Total estimated construction cost, updated each year end. |
| 실행예산 | silhaeng-yesan | Execution budget: the working cost budget for a site, often called 실행. |
| 분양률 | bunyangnyul | Sales ratio: the share of units sold under signed contracts. |
| 감리확인공정률 | gamni-hwagin-gongjeongnyul | Construction progress certified by the supervisor. |
| 중소기업회계기준 | jungsogieop-hoegye-gijun | SME Accounting Standard for stock companies not subject to external audit. |
| 건축공정확인서 | geonchuk-gongjeong-hwaginseo | Construction progress certificate issued by the supervisor before interim payments are called. |
Sources
- Corporate Tax Act, Article 40 (법인세법 제40조): https://www.law.go.kr/법령/법인세법
- Enforcement Decree of the Corporate Tax Act, Article 69 (법인세법 시행령 제69조): https://www.law.go.kr/법령/법인세법시행령
- Enforcement Rule of the Corporate Tax Act, Article 34 (법인세법 시행규칙 제34조): https://www.law.go.kr/법령/법인세법시행규칙
- National Tax Service rulings 법인세과-760 (2009.7.2.), 법인세과-2354 (2008.9.5.), 법인세과-1151 (2009.10.16.): https://taxlaw.nts.go.kr
- SME Accounting Standard, Articles 2 and 24 (중소기업회계기준 고시 제2조·제24조), Ministry of Justice notice
- Enforcement Decree of the Commercial Act, Article 15 (상법 시행령 제15조): https://www.law.go.kr/법령/상법시행령
- Rules on Housing Supply, Article 60 (주택공급에 관한 규칙 제60조): https://www.law.go.kr/법령/주택공급에관한규칙
This guide explains general rules as of Nov 20, 2026. It is not legal or tax advice. Laws and forms change, so check the official website or ask a licensed professional before you act.